Petrochemical
Petrochemical Projects
Selected project references across nuclear and thermal power, desalination, petrochemical, boilers and heating, and HVAC. Filter by industry, type of work, year and tube material, or read about featured projects in detail.
Featured projects
Selected project references
Translated from our Chinese project records. Plant and client names are given as they were at the time of each project.
| Project | Unit rating | Date | Tube material | Scope |
|---|---|---|---|---|
| Retubing at Jinshan (Sinopec Shanghai Petrochemical Co., Ltd.) | 1 unit | Dec 2025 | Copper alloy | Retubing |
| Sinopec-SK (Wuhan) Petrochemical Project (Hangzhou Guoneng, WB2025-LB-06Q) | 1 unit | Dec 2025 | Stainless steel | Retubing |
| Heat Exchanger Tube Supply and Retubing (Fujian Meide Petrochemical Co., Ltd.) | 1 unit | Apr 2025 | Copper alloy | Retubing |
| Retubing at Zhejiang Petrochemical | Nov 2023 | Titanium | Retubing | |
| Condenser Retubing, Ethylene Unit 2 Turnaround, Olefins Division (Sinopec Shanghai Petrochemical Co., Ltd.) | 3 units | Sep 2023 | Copper alloy | Retubing |
| Copper Tube Replacement on E-EA1215, Ethylene Complex Turnaround (Sinopec Yangzi Petrochemical Co., Ltd.) | 1 unit | Apr 2022 | Copper alloy | Retubing |
| Inspection and Maintenance (Sinopec Shanghai Petrochemical Co., Ltd.) | 2 units | May 2021 | Copper alloy | Retubing |
| Retubing of Three Turbine Condensers, BCC Unit, BASF-YPC, Nanjing | 50 MW | Apr 2015 | Stainless steel | Retubing |
| Unit 1 Condenser Overhaul (Tianjin Jinbin Petrochemical Equipment Co., Ltd.) | 50 MW | Nov 2014 | Stainless steel | Tube-end coating |
| Copper Tube Replacement on Condenser E-EA215, Ethylene Unit, Yangzi Petrochemical Olefins Plant | 12 MW | Aug 2014 | Copper alloy | Retubing |
| Cogeneration Division, Sinopec Baling Petrochemical | 15 MW | Feb 2008 | Copper alloy | Retubing |
| Nanjing Meishan Petrochemical | 12 MW | Nov 2007 | Copper alloy | Retubing |
| Sinopec Shanghai Petrochemical Co., Ltd. | Ethylene unit | Jul 2007 | Copper alloy | Retubing |
| Tianjin Petrochemical Cogeneration Plant | 50 MW | Apr 2005 | Stainless steel | Retubing |
| Tianjin Chemical Cogeneration Plant | 12 MW | May 2004 | Stainless steel | Retubing |
| Yueyang Petrochemical Cogeneration Plant | 12 MW | Mar 2004 | Copper alloy | Retubing |
| Yueyang Petrochemical Cogeneration Plant, Hunan | 12 MW | May 2001 | Copper alloy | Retubing |
| Hangzhou Guoneng Turbine Engineering Co., Ltd. | 15 units | In progress | Titanium, copper alloy, stainless steel | Cleaning, expanding, trimming, facing & welding |
Request a quote
Send us your equipment details
Drawings or site photos help. We will go through the equipment, tube material and outage window with you, and send an engineer to site if an inspection is needed.
During our working hours (UTC+8) we usually reply within two hours.