Project facts
| Client / owner | Guangdong Thermal Power Construction Co. (Unit 3, Sanbaimen Power Plant, Raoping, Guangdong) |
|---|---|
| Industry | Thermal Power |
| Equipment | Condenser |
| Rating / size | 1,000 MW |
| Tube material | Titanium |
| Quantity | Nearly 40,000 tubes |
| Duration | 15 days for expansion, trimming and welding |
| Project date | February 2009 |
| Result | Hydrostatic test passed on the first attempt, with no leaks. |
In February 2009, Guangdong Thermal Power Construction Co. brought in Lanbo for tube installation, expansion, trimming and welding on the condenser of the 1,000 MW Unit 3 at Sanbaimen Power Plant in Raoping. Nearly 40,000 titanium tubes were expanded, trimmed, faced and welded in 15 days, and the condenser passed its hydrostatic test on the first attempt with no leaks.
These figures are for this project only. Schedules for other jobs depend on the tube count, tube material, site conditions and the outage window.
Related services
Planning a similar job? Send us your equipment details
Request a QuoteRelated projects

Thermal Power
Condenser Retrofit at a Power Plant in Myanmar
Hangzhou Guoneng Turbine Engineering Co., Ltd. Quote for a similar job
Thermal Power
Luoyuan Bay Unit 2, Fuzhou: Condenser Steam-side Cleaning, Titanium Tubing & Welding
Harbin Shunyuan Power Plant Equipment Co., Ltd. Quote for a similar job
Thermal Power