Lakvijaya Power Plant, Sri Lanka: 300 MW Condenser Retrofit

Titanium condenser tube installation, expansion, trimming, facing and welding completed; the Sri Lankan owner recognised the work.

Published 31 Jul 2015 · Updated 20 Oct 2026

Project facts

Client / ownerHarbin Turbine Auxiliary Equipment Engineering Co., Ltd. (Lakvijaya Power Plant, Sri Lanka)
IndustryThermal Power
EquipmentCondenser
Rating / size2 × 300 MW
Tube materialTitanium
Duration90 days of continuous work
Project dateJuly to October 2015 (completed 23 October)
ResultTitanium condenser tube installation, expansion, trimming, facing and welding completed; the Sri Lankan owner recognised the work.

Lanbo carried out the titanium condenser tube installation, expansion, trimming, facing and welding retrofit in Sri Lanka under a contract signed with Harbin Turbine Auxiliary Equipment Engineering Co., Ltd. on 20 August 2015. The plant has two 300 MW units and is one of the largest power plants in Sri Lanka.

Lanbo's crew worked for 90 days without a break and finished on 23 October 2015, using retubing tools Lanbo designs and builds in-house. The Sri Lankan owner recognised the quality of the work.