# Lakvijaya Power Plant, Sri Lanka: 300 MW Condenser Retrofit

- Industries: Thermal Power
- Client: Harbin Turbine Auxiliary Equipment Engineering Co., Ltd. (Lakvijaya Power Plant, Sri Lanka)
- Equipment: Condenser
- Unit / size: 2 × 300 MW
- Tube material: Titanium
- Duration: 90 days of continuous work
- Date: July to October 2015 (completed 23 October)
- Result: Titanium condenser tube installation, expansion, trimming, facing and welding completed; the Sri Lankan owner recognised the work.

Lanbo carried out the titanium condenser tube installation, expansion, trimming, facing and welding retrofit in Sri Lanka under a contract signed with Harbin Turbine Auxiliary Equipment Engineering Co., Ltd. on 20 August 2015. The plant has two 300 MW units and is one of the largest power plants in Sri Lanka.

Lanbo's crew worked for 90 days without a break and finished on 23 October 2015, using retubing tools Lanbo designs and builds in-house. The Sri Lankan owner recognised the quality of the work.

## Related services

- [Condenser Retubing](https://www.heatexchangersolution.com/en/services/condenser-retubing/)

Web page: https://www.heatexchangersolution.com/en/projects/lakvijaya-sri-lanka/

---
Contact Lanbo: +86 136 3706 9797 · Lanbo@hflanbo.com.cn · https://www.heatexchangersolution.com/en/contact/