Service Hotline
+86-13637066767+86-551-62884258
Project Name |
Installed Capacity |
Construction Period |
Tube Material |
Note |
Salaqi Power Plant |
/ |
2016.11 |
|
Tube Replacement |
North China Power Baotou No. 2 Thermal Power Plant |
300 MW |
2015.8 |
Stainless Steel |
Tube Replacement |
Copper Tube Replacement Project of Oil Cooler for Unit #04(Nanjing Meishan Thermal Power Plant) |
100 MW |
2015.4 |
Copper |
Tube Replacement |
Jiangsu Xielian Yixing Thermal Power Co., Ltd. |
125MW |
2007.1 |
Copper |
Tube Replacement |
Donggang Thermal Power Plant, Jinzhou, Liaoning |
200MW |
2005.1 |
Stainless Steel |
Tube Replacement |
Donggang Thermal Power Plant, Jinzhou |
200MW |
2004.10 |
Copper |
Tube Replacement |
Huai’an Thermal Power Plant |
12MW |
2004.10 |
Copper |
Tube Replacement |
Taiyuan No.1 Thermal Power Plant |
135MW |
2004.7 |
Stainless Steel |
Tube Replacement |
Shanxian Thermal Power Plant, Henan |
50MW |
2004.5 |
Stainless Steel |
Tube Replacement |
Qingshan Thermal Power Plant, Hubei |
100MW |
2004.3 |
Copper |
Tube Replacement |
Yixing Thermal Power Plant, Jiangsu |
50MW |
2004.2 |
Copper |
Tube Replacement |
Fengcheng Thermal Power Plant, Liaoning |
6MW |
2003.10 |
Copper |
Tube Replacement |
Taiyuan No. 2 Thermal Power Plant, Shanxi |
50MW |
2003.3 |
Copper |
Tube Replacement |
Wantong Thermal Power Plant, Yantai |
25MW |
2002.12 |
Copper |
Tube Replacement |
Dongtang Group Thermal Power Plant, Dongguan |
25MW |
2002.7 |
Copper |
Tube Replacement |
Dongtang Group Thermal Power Plant, Dongguan |
12MW |
2002.6 |
Copper |
Tube Replacement |
Harbin Chemical Thermal Power Co., Ltd. |
12MW |
2001.7 |
Copper |
Tube Replacement |
Liaohe Thermal Power Plant Unit #3 |
50MW |
2001.6 |
Copper |
Tube Replacement |
Ogden Madian Thermal Power Plant, Taixing, Jiangsu |
12MW |
2000.12 |
Copper |
Tube Replacement |
Jiangyuan Thermal Power Co., Ltd. |
6MW |
1999.12 |
Copper |
Tube Replacement |
Xielian Thermal Power Plant, Yixing, Jiangsu |
12MW |
1999.8 |
Copper |
Tube Replacement |
Chaoyang Thermal Power Plant, Liaoning |
6MW |
1999.3 |
Copper |
Tube Replacement |
Xiangcheng Thermal Power Plant, Henan |
12MW |
1998.8 |
Copper |
Tube Replacement |
Xiangcheng Thermal Power Plant, Henan |
3MW |
1998.6 |
Copper |
Tube Replacement |
b.Modification
Project Name |
Installed Capacity |
Construction Period |
Tube Material |
Note |
On-site Installation of Condenser for Baotou Aluminium |
2 units (125MW) |
2017.10 |
Stainless Steel |
Modification |
On-site Installation of Condenser for Xingneng Power |
5 units |
2017.10 |
Stainless Steel |
Modification |
Condenser Installation at Shanxi Xingneng (Gujiao) Power |
80000㎡ |
2016.6 |
Stainless Steel |
Modification |
Jinqiao Condenser Project |
300MW |
2014.8 |
Stainless Steel |
Modification |
c.Installation of New Unit
Project Name |
Installed Capacity |
Construction Period |
Tube Material |
Note |
|
|
|
|
|