Project Name |
Installed Capacity |
Construction Period |
Tube Material |
Note |
|
Salaqi Power Plant |
/ |
2016.11 |
|
Tube Replacement |
|
North China Power Baotou No. 2 Thermal Power Plant |
300 MW |
2015.8 |
Stainless Steel |
Tube Replacement |
|
Copper Tube Replacement Project of Oil Cooler for Unit #04(Nanjing Meishan Thermal Power Plant) |
100 MW |
2015.4 |
Copper |
Tube Replacement |
|
Jiangsu Xielian Yixing Thermal Power Co., Ltd. |
125MW |
2007.1 |
Copper |
Tube Replacement |
|
Donggang Thermal Power Plant, Jinzhou, Liaoning |
200MW |
2005.1 |
Stainless Steel |
Tube Replacement |
|
Donggang Thermal Power Plant, Jinzhou |
200MW |
2004.10 |
Copper |
Tube Replacement |
|
Huai’an Thermal Power Plant |
12MW |
2004.10 |
Copper |
Tube Replacement |
|
Taiyuan No.1 Thermal Power Plant |
135MW |
2004.7 |
Stainless Steel |
Tube Replacement |
|
Shanxian Thermal Power Plant, Henan |
50MW |
2004.5 |
Stainless Steel |
Tube Replacement |
|
Qingshan Thermal Power Plant, Hubei |
100MW |
2004.3 |
Copper |
Tube Replacement |
|
Yixing Thermal Power Plant, Jiangsu |
50MW |
2004.2 |
Copper |
Tube Replacement |
|
Fengcheng Thermal Power Plant, Liaoning |
6MW |
2003.10 |
Copper |
Tube Replacement |
|
Taiyuan No. 2 Thermal Power Plant, Shanxi |
50MW |
2003.3 |
Copper |
Tube Replacement |
|
Wantong Thermal Power Plant, Yantai |
25MW |
2002.12 |
Copper |
Tube Replacement |
|
Dongtang Group Thermal Power Plant, Dongguan |
25MW |
2002.7 |
Copper |
Tube Replacement |
|
Dongtang Group Thermal Power Plant, Dongguan |
12MW |
2002.6 |
Copper |
Tube Replacement |
|
Harbin Chemical Thermal Power Co., Ltd. |
12MW |
2001.7 |
Copper |
Tube Replacement |
|
Liaohe Thermal Power Plant Unit #3 |
50MW |
2001.6 |
Copper |
Tube Replacement |
|
Ogden Madian Thermal Power Plant, Taixing, Jiangsu |
12MW |
2000.12 |
Copper |
Tube Replacement |
|
Jiangyuan Thermal Power Co., Ltd. |
6MW |
1999.12 |
Copper |
Tube Replacement |
|
Xielian Thermal Power Plant, Yixing, Jiangsu |
12MW |
1999.8 |
Copper |
Tube Replacement |
|
Chaoyang Thermal Power Plant, Liaoning |
6MW |
1999.3 |
Copper |
Tube Replacement |
|
Xiangcheng Thermal Power Plant, Henan |
12MW |
1998.8 |
Copper |
Tube Replacement |
|
Xiangcheng Thermal Power Plant, Henan |
3MW |
1998.6 |
Copper |
Tube Replacement |
b.Modification
|
Project Name |
Installed Capacity |
Construction Period |
Tube Material |
Note |
|
On-site Installation of Condenser for Baotou Aluminium |
2 units (125MW) |
2017.10 |
Stainless Steel |
Modification |
|
On-site Installation of Condenser for Xingneng Power |
5 units |
2017.10 |
Stainless Steel |
Modification |
|
Condenser Installation at Shanxi Xingneng (Gujiao) Power |
80000㎡ |
2016.6 |
Stainless Steel |
Modification |
|
Jinqiao Condenser Project |
300MW |
2014.8 |
Stainless Steel |
Modification |
c.Installation of New Unit
|
Project Name |
Installed Capacity |
Construction Period |
Tube Material |
Note |
|
|
|
|
|
|